September 2015
Endesa has launched the project of modernization of the power station of Carboneras (Almería) which will involve an investment of about 200 million euros.
This project includes the construction of systems of denitrification of two groups of the central and the improvement of desulphurisation of the group 2, to fulfil with the values of broadcast demanded by the European Directive 2010/75
Along the 18 months that roughly will last the works, EUROGRUAS will contribute to the project with teams of elevation and of transport of different capacities, highlighting for the works of heavy lift a crawler crane of 600 t Terex Demag CC2800-1.